Schedule for the mining project
2019
Preliminary economic assessment
2020
Pre-feasibility study
2022
Analysis of implementation options
2022
A feasibility study is launched.
11/2022
The road plan for the mining road is approved. The plan envisages the construction of a road access to the mining area of about 10 km from the Rovaniemi-Ranua trunk road: about 8.5 km of road from the trunk road to the border of the mining district and 1.5 km of private road inside the mining area.
19.6.2023
The contract for the Suhanko mine is signed. The contract is awarded by the Finnish Transport Agency.
The contractor is GRK Finland Oy.
The subcontractor is J Vainio from Kittilä.
07/2023
Construction of the mine road begins.
2023
Application to update the environmental and water management permit
2024
A financing decision is expected
2024
The aim is to complete the mine by autumn
2024
Aim to start construction work
2026
The aim is to start production