Schedule for the mining project
2019
Preliminary economic assessment
2020
Pre-feasibility study
2022
Analysis of implementation options
2022
A feasibility study is launched.
11/2022
The road plan for the mining road is approved. The plan envisages the construction of a road access to the mining area of about 10 km from the Rovaniemi-Ranua trunk road: about 8.5 km of road from the trunk road to the border of the mining district and 1.5 km of private road inside the mining area.
19.6.2023
The contract for the Suhanko mine is signed. The contract is awarded by the Finnish Transport Agency.
The contractor is GRK Finland Oy.
The subcontractor is J Vainio from Kittilä.
07/2023
Construction of the mine road begins.
2023
Application to update the environmental and water management permit
10/2024
The mining road is completed
12/2024
The Finnish Safety and Chemicals Agency Tukes has granted Suhanko Arctic Platinum Oy an auxiliary area for the Suhanko mining district in accordance with the Mining Act. With this permit, the Suhanko mining district is granted an auxiliary mining area for the construction of an extraction tunnel pursuant to Section 19 of the Mining Act.
Q1/2025
Clearing of the Petäjäskoski-Konttijärvi power line begins
H1/2025
Decision on the environmental and water management permit
Q3/2025
Preparations for the construction of the discharge pipeline are underway. The aim is to take a decision on the construction of the mine
Q4/2025
Profitability study of the mine is completed
2026
Construction of the mine starts
2027
Production at the mine starts